How to use the OEE calculator
- Enter the shift length and the planned downtime (breaks, meetings, no orders). The difference is the planned production time — the time the machine was supposed to run.
- Enter the stop time: breakdowns and setup/changeover minutes.
- Enter the ideal cycle time (or the ideal run rate — choose the unit) and the total count and rejects.
- Read availability, performance, quality and OEE, then look at the waterfall and the six-big-losses table to see where the time went. Add the calendar time to get TEEP.
- For several shifts, days or machines, switch to Table of shifts or machines and paste or upload one row per run.
The OEE formulas
| Quantity | Formula |
|---|---|
| Planned production time | Shift length − planned downtime |
| Run time | Planned production time − stop time |
| Availability | Run time ÷ planned production time |
| Performance | (Ideal cycle time × total count) ÷ run time |
| Quality | Good count ÷ total count |
| OEE | Availability × Performance × Quality = (good count × ideal cycle time) ÷ planned production time |
| TEEP | OEE × (planned production time ÷ calendar time) |
The last form of the OEE formula is the most useful way to think about it: OEE is the share of planned time that was spent making good parts at the ideal speed. Everything else is loss. TEEP (total effective equipment performance) measures against all calendar time, 24 hours a day, so it also shows unscheduled capacity.
The six big losses
| OEE factor | Loss | Examples |
|---|---|---|
| Availability | Equipment failure | Breakdowns, tooling failure, waiting for maintenance or material |
| Setup and adjustments | Changeovers, warm-up, first-off approval | |
| Performance | Idling and minor stops | Jams, blocked sensors, short stops usually under five minutes |
| Reduced speed | Running below the ideal rate, wear, operator inefficiency | |
| Quality | Process defects | Scrap and rework in steady production |
| Reduced yield | Scrap from startup until stable running |
The calculator converts every loss into minutes of planned production time, so the six losses and the fully productive time add up exactly. A Pareto chart of the stop reasons is the natural next step.
What is a good OEE?
- 85% is the classic world-class benchmark, built from 90% availability, 95% performance and 99.9% quality.
- 60% is typical for discrete manufacturing.
- 40% is common where OEE has only just started to be measured.
Treat these figures with caution. They come from one industry context; a high-mix plant with many changeovers cannot be compared with a dedicated line. OEE is best used to track one machine against its own history. And maximising OEE on a non-bottleneck machine only produces inventory — schedule to takt time first.
Worked example
Data: 480-minute shift, 60 minutes of breaks, 47 minutes of stops (35 breakdown + 12 changeover), ideal cycle time 3 seconds, 6,800 parts made, 136 rejected.
Planned production time = 480 − 60 = 420 min. Run time = 420 − 47 = 373 min.
Availability = 373 ÷ 420 = 88.8%.
Performance = (3 s × 6,800) ÷ 373 min = 340 min ÷ 373 min = 91.2%.
Quality = (6,800 − 136) ÷ 6,800 = 6,664 ÷ 6,800 = 98.0%.
OEE = 0.888 × 0.912 × 0.980 = 79.3%. Check: 6,664 good parts × 3 s = 333.2 min of fully productive time; 333.2 ÷ 420 = 79.3%.
TEEP over a 24-hour day = 79.3% × 420 ÷ 1,440 = 23.1%.
Why you must not average OEE percentages
Suppose a full 420-minute shift runs at 80% OEE and a 60-minute trial run achieves 20%. The simple average is 50%, but the machine produced 0.80 × 420 + 0.20 × 60 = 348 good-equivalent minutes out of 480 planned — a true OEE of 72.5%. Percentages with different denominators cannot be averaged. The multi-row mode therefore sums the underlying times: total OEE = Σ fully productive time ÷ Σ planned production time, which is the same as weighting each row by its planned production time. The same applies to availability, performance and quality. The tool shows the simple average next to the weighted figure so you can see the size of the error.
Checks and pitfalls
- Performance above 100% means the ideal cycle time is too generous (use the nameplate or best demonstrated rate, not a budget standard), or stops are over-reported. The tool flags it.
- Do not hide losses in planned downtime. Changeovers belong in availability losses; only time when production was genuinely not scheduled is excluded.
- Rework counts as a reject — OEE quality is first-pass yield.
- Use a consistent ideal cycle time per product. With a product mix, enter one row per product run in the multi-row mode.
Definitions follow Nakajima, Introduction to TPM, and common industry practice (SEMI E10/E79 use related but not identical definitions).
Frequently asked questions
How do you calculate OEE?
OEE = Availability × Performance × Quality. Availability is run time divided by planned production time, performance is ideal cycle time times total count divided by run time, and quality is good count divided by total count. Equivalently, OEE is good count times ideal cycle time divided by planned production time.
What is a good OEE score?
About 85% is considered world class for discrete manufacturing, 60% is typical and 40% is common for plants beginning to measure OEE. These are rough guides; the right target depends on the process, product mix and changeover frequency.
What is the difference between OEE and TEEP?
OEE measures effectiveness during planned production time. TEEP (total effective equipment performance) measures against all calendar time, 24 hours a day and 7 days a week, so TEEP = OEE × utilisation, where utilisation is planned production time divided by calendar time.
Why is my performance above 100%?
Performance above 100% means more parts were produced than the ideal cycle time allows in the recorded run time. Usually the ideal cycle time is set too slow, for example a budget standard rather than the true best rate, or the stop time was overstated.
How do I combine OEE across shifts or machines?
Do not average the percentages. Add up the planned production time, run time, net run time and fully productive time of all rows and compute the factors from the totals. This weights each shift or machine by its planned production time.
Are breaks and changeovers included in OEE?
Scheduled breaks and periods with no planned production are excluded from planned production time, so they do not reduce OEE (they do reduce TEEP). Changeovers and setups are counted as availability losses, because the machine was scheduled to produce.